TOGAF Enterprise Architecture Foundation — Question 57
What are the following activities part of?
• Risk classification
• Risk identification
• Initial risk assessment
Answer options
- A. Phase G
- B. Security Architecture
- C. Phase A
- D. Risk Management
Correct answer: D
Explanation
The correct answer is D, Risk Management, as it encompasses risk classification, identification, and initial assessment. Options A and C refer to specific phases in a broader framework and do not include these activities, while B, Security Architecture, focuses on designing security structures rather than risk-related tasks.