TOGAF Enterprise Architecture Foundation — Question 11
What is an objective of the ADM Implementation Governance Phase?
Answer options
- A. To ensure conformance for the target architecture
- B. To establish the resources for architecture governance
- C. To provide continual monitoring of the governance framework
- D. To finalize the Implementation and Migration Plan
Correct answer: A
Explanation
The correct answer is A because the primary objective of the ADM Implementation Governance Phase is to ensure that the implemented architecture aligns with the target architecture. Options B and C are related to governance but do not directly address the conformance aspect, while option D pertains to the planning stage rather than governance.