TOGAF 9 Combined Part 1 and Part 2 — Question 307
In which part of the ADM cycle do building block gaps become associated with work packages that will address the gaps?
Answer options
- A. Preliminary Phase and Phase A
- B. Phases B, C, and D
- C. Phase E
- D. Phase F
- E. Phases G and H
Correct answer: C
Explanation
The correct answer is Phase E, as this is when the work packages are developed to address the identified gaps in the building blocks. The other phases do not focus on work package creation related to building block gaps, making them incorrect options.