TOGAF 9 Combined Part 1 and Part 2 — Question 279
Complete the sentence. The Requirements Management Phase _____________________.
Answer options
- A. addresses and resolves requirements between ADM phases
- B. is a central process that prioritizes requirements for all ADM phases
- C. is used to dispose of resolved requirements for all ADM phases
- D. generates new requirements and passes them to all ADM phases
- E. stores requirements and manages their flow into relevant ADM phases
Correct answer: E
Explanation
The correct answer, E, accurately describes the role of the Requirements Management Phase in overseeing the flow of requirements into relevant ADM phases. Options A, B, C, and D do not capture the primary function of this phase, which is to store and manage requirements rather than prioritize, resolve, dispose of, or generate new ones.