TOGAF 9 Combined Part 1 and Part 2 — Question 271

In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?

Answer options

Correct answer: E

Explanation

The correct answer is E, as Phase F focuses on the migration planning and ensures that the Implementation and Migration Plan is synchronized with other enterprise activities. The other phases do not specifically address the coordination of the Implementation and Migration Plan with other activities.