TOGAF 9 Combined Part 1 and Part 2 — Question 271
In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?
Answer options
- A. Phase A
- B. Phase G
- C. Phase E
- D. Phase H
- E. Phase F
Correct answer: E
Explanation
The correct answer is E, as Phase F focuses on the migration planning and ensures that the Implementation and Migration Plan is synchronized with other enterprise activities. The other phases do not specifically address the coordination of the Implementation and Migration Plan with other activities.