TOGAF 9 Combined Part 1 and Part 2 — Question 205
What level of risk is the risk categorization prior to determining and implementing mitigating actions?
Answer options
- A. Critical
- B. Residual
- C. Low
- D. Marginal
- E. Initial
Correct answer: E
Explanation
The correct answer is 'Initial' because it represents the risk level assessed before any mitigation strategies are applied. The other options refer to risk levels after mitigation has occurred or suggest a different context of risk assessment.