TOGAF 9 Combined Part 1 and Part 2 — Question 188

In which ADM phase does the value and change management process determine the circumstances under which the Enterprise Architecture is permitted to change after deployment?

Answer options

Correct answer: D

Explanation

The correct answer is D, Phase H, where the change management process is defined to manage modifications to the Enterprise Architecture after it has been implemented. The other phases (A, B, C, and E) focus on different aspects of the ADM and do not specifically address post-deployment change management.