TOGAF 9 Combined Part 1 and Part 2 — Question 170

Which phase of the ADM focuses on the governance and management of the Architecture Con-tracts that cover the overall implementation and deployment process?

Answer options

Correct answer: D

Explanation

Phase G is dedicated to the governance and management aspects of Architecture Contracts, ensuring that the implementation aligns with the established architecture. The other phases, while important, do not specifically address the governance of contracts related to deployment and implementation.