TOGAF 9 Combined Part 1 and Part 2 — Question 152
Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project?
Answer options
- A. Architecture Change Management
- B. Implementation governance
- C. Migration planning
- D. Preliminary Phase
- E. Requirements Management
Correct answer: E
Explanation
The correct answer is E, Requirements Management, as it is a crucial, iterative phase that ensures requirements are continuously addressed throughout the project. The other options represent distinct phases or governance elements that do not involve the ongoing assessment of requirements.