TOGAF 9 Certified (Level 2) — Question 29
RIG Networks, a global network supplier is implementing a massive replacement of its supply chain to reduce production cost of their new LTE (Long Term
Evolution) gateways. As part of this renovation process the CIO decided to replace their ERP (Enterprise Resource Planning) system using a greenfield approach
(where the legacy ERP system will be decommissioned). The CIO engaged a team of TOGAF 9 certified consultants to design the solution, he then identified the suppliers and asked you as Chief Architect to supervise the definition of the Architecture Design and Development Contract.
You now need to write the Architecture Design and Development Contract, identify how you would o this following TOGAF 9.
Choose one of the following answers
Answer options
- A. You would define the Architecture Design and Development Contract with : introduction and background, the nature of the agreement, scope of the architecture, architecture and strategic principles and requirements, conformance requirements, Target Architecture Measures, Define phases of deliverables, Prioritized joint workplan, Time window, Architecture delivery and business metrics.
- B. You would define the Architecture Design and Development Contract with : introduction and background, the nature of the agreement, scope of the architecture, architecture and strategic principles and requirements, conformance requirements, Baseline Architecture definition, Target Architecture Measures, Define phases of deliverables, Prioritized joint workplan, Time window, Architecture delivery and business metrics.
- C. You would define the Architecture Design and Development Contract with : Target Architecture Measures, Define phases of deliverables, Prioritized joint workplan, Time window, Architecture delivery and business metrics.
- D. You would define the Architecture Design and Development Contract with : scope, goals, objectives and constraints, Architecture Principles, Baseline Architecture, Architecture Models, Gap Analysis, Impact Assessment.
Correct answer: A
Explanation
The correct answer, A, includes all the necessary components for a comprehensive Architecture Design and Development Contract as per TOGAF 9 guidelines, ensuring that all aspects of the architecture are covered. Options B and D introduce elements like Baseline Architecture and Gap Analysis, which are not essential for this specific contract. Option C is too limited as it lacks key components such as the introduction, scope, and strategic principles.