TOGAF 9 Foundation (Level 1) — Question 276
Which phase of the TOGAF ADM is the first phase directly concerned with the planning for the implementation of the target architecture(s)?
Answer options
- A. Phase D
- B. Phase E
- C. Phase F
- D. Phase G
- E. Phase H
Correct answer: B
Explanation
Phase E of the TOGAF ADM is dedicated to planning the implementation of target architectures, making it the correct choice. Other phases, such as Phase D, focus on the requirements and architecture design, while Phases F, G, and H deal with migration planning, implementation governance, and architecture change management respectively, which do not directly address implementation planning.