TOGAF 9 Foundation (Level 1) — Question 240
What is an objective of the ADM Preliminary Phase?
Answer options
- A. To create the initial version of the Architecture Roadmap
- B. To develop a vision of the business value to be delivered by the proposed enterprise architecture
- C. To select and implement tools to support the Architecture Capability
- D. To obtain approval for the Statement of Architecture Work
- E. To document the baseline architecture
Correct answer: C
Explanation
The correct answer is C because the Preliminary Phase focuses on establishing the architecture capability, which includes selecting and implementing necessary tools. The other options pertain to different phases or objectives within the ADM process, such as creating roadmaps or documenting architectures, which are not the primary aim of the Preliminary Phase.