TOGAF 9 Foundation (Level 1) — Question 24
The Requirements Management Phase is responsible for which one of the following activities?
Answer options
- A. Addressing requirements
- B. Disposal of resolved requirements
- C. Generating requirements
- D. Managing the flow of requirements
- E. Prioritizing requirements
Correct answer: D
Explanation
The correct answer is D because the Requirements Management Phase focuses on managing how requirements are tracked and communicated throughout the project. Options A, B, C, and E, while related to requirements, do not specifically pertain to the management of their flow, which is the key responsibility during this phase.