TOGAF 9 Foundation (Level 1) — Question 217
Complete the sentence. The Requirements Management process is used to______.
Answer options
- A. develop requirements for Transition Architectures that deliver business value
- B. dispose of, address and prioritize architecture requirements
- C. organize architecture requirements throughout the ADM cycle
- D. review business requirements
- E. validate requirements between ADM phases
Correct answer: C
Explanation
The correct answer is C because the Requirements Management process is specifically focused on organizing architecture requirements throughout the Architecture Development Method (ADM) cycle. Options A, B, D, and E describe different aspects of requirements management but do not accurately capture the primary function of organizing requirements.