TOGAF 9 Foundation (Level 1) — Question 197
In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?
Answer options
- A. Phase A
- B. Phase E
- C. Phase F
- D. Phase G
- E. Phase H
Correct answer: C
Explanation
The correct answer is Phase F, where the Implementation and Migration Plan is developed and coordinated with other relevant frameworks to ensure alignment and coherence. The other phases do not specifically focus on the coordination of the implementation plan with other frameworks, thus making them incorrect options.