TOGAF 9 Foundation (Level 1) — Question 175

Which one of the following is responsible for the acceptance and sign-off of an Architecture Compliance review?

Answer options

Correct answer: A

Explanation

The Architecture Board is the entity that oversees and authorizes the outcomes of an Architecture Compliance review. The other options, while important roles, do not hold the formal responsibility for the acceptance and sign-off of such reviews.