TOGAF 9 Foundation (Level 1) — Question 162
Complete the sentence. The Requirements Management Phase ___________.
Answer options
- A. addresses and resolves requirements between ADM phases
- B. is a central process that prioritizes requirements for all ADM phases
- C. is used to dispose of resolved requirements for all ADM phases
- D. generates new requirements and passes them to all ADM phases
- E. stores requirements and manages their flow into relevant ADM phases
Correct answer: E
Explanation
The correct answer, E, accurately describes the role of the Requirements Management Phase in overseeing the flow of requirements into the relevant ADM phases. Option A is incorrect because it implies resolving requirements rather than managing them. Option B mischaracterizes the phase as primarily focused on prioritization instead of management. Option C inaccurately suggests that the phase disposes of resolved requirements, while D incorrectly states that it generates new requirements.