TOGAF 9 Foundation (Level 1) — Question 150

In Phase G, What document establishes the connection between the architecture organization and the implementation organization?

Answer options

Correct answer: A

Explanation

The Architecture Contract is the correct answer as it formalizes the agreement between the architecture and implementation teams, detailing expectations and commitments. The other documents, while relevant to architecture, do not specifically establish this crucial connection.