TOGAF 9 Foundation (Level 1) — Question 117
Which one of the following is an objective of the Preliminary Phase of the ADM?
Answer options
- A. To define the Baseline Architecture for this cycle of the ADM
- B. To define the application systems for the Target Architecture
- C. To define the framework and methodologies to be used
- D. To define the relevant stakeholders and their concerns
- E. To define and prioritise work packages
Correct answer: C
Explanation
The correct answer is C because the Preliminary Phase focuses on establishing the framework and methodologies for the ADM process. Options A, B, D, and E pertain to objectives that are addressed in later phases of the ADM rather than the Preliminary Phase.