TOGAF 9 Foundation (Level 1) — Question 100
What is an objective of ADM Phase G, Implementation Governance?
Answer options
- A. To ensure that implementation projects conform with the Target Architecture
- B. To ensure that the enterprise's Architecture Capability meets current requirements
- C. To assess the performance of the architecture and make recommendations for change
- D. To establish the value realization process
- E. To prioritise the projects through risk validation
Correct answer: A
Explanation
The correct answer is A, as the primary objective of Phase G is to ensure that all implementation projects adhere to the established Target Architecture. Options B, C, D, and E, while relevant to architecture governance and management, do not specifically address the compliance aspect of implementation projects with the Target Architecture.