Tableau Desktop Specialist — Question 151
What is an ideal use case for using a Gantt chart in Tableau?
Answer options
- A. To analyze trends of budget growth in a project over multiple quarters
- B. To analyze correlation between project resourcing and quality
- C. To display the timeline of project tasks and their durations
- D. To compare performance of a project across different regions
Correct answer: C
Explanation
The correct answer is C because a Gantt chart is specifically designed to visualize the timeline and duration of project tasks. Options A, B, and D are not appropriate uses of a Gantt chart as they focus on analysis rather than task scheduling and timing.