Splunk Enterprise Certified Architect — Question 88
Which of the following should be included in a deployment plan?
Answer options
- A. Business continuity and disaster recovery plans.
- B. Current logging details and data source inventory.
- C. Current and future topology diagrams of the IT environment.
- D. A comprehensive list of stakeholders, either direct or indirect.
Correct answer: B
Explanation
Option B is correct because having current logging details and a data source inventory is essential for tracking and managing the deployment process. Options A, C, and D are important but do not specifically pertain to the technical aspects of deployment as much as option B does.