Lean Six Sigma Yellow Belt (LSSYB) — Question 7
A Belt gathered the following defect data for a polyurethane production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data: Trimming 37 -
Forming 61 -
Packaging 29 -
Sealing 5 -
Answer options
- A. Trimming, Packaging, Sealing, Forming
- B. Packaging, Trimming, Sealing, Forming
- C. Sealing, Forming, Trimming, Packaging
- D. Forming, Sealing, Trimming, Packaging
Correct answer: D
Explanation
The correct answer is D, as the defects are arranged in descending order of frequency: Forming (61), Trimming (37), Packaging (29), and Sealing (5). The other options do not reflect this order, which is essential for a Pareto Chart that emphasizes the most significant issues first.