What is the Ppk of a process with a spread of 24 units, an average of 68, an upper limit of 82 and a lower limit of 54?

Answer options

Correct answer: C

Explanation

The Ppk is calculated based on the process average, the specification limits, and the standard deviation. In this case, the spread and limits result in a Ppk of 4.00, which indicates a capable process. The other options do not reflect the correct calculation based on the provided parameters.