IASSC Certified Lean Six Sigma Green Belt (ICGB) — Question 14

The use of Kanbans work best with pull systems for determining the timing of which products or services are produced.

Answer options

Correct answer: A

Explanation

The correct answer is True because Kanbans are designed to signal when more products or services are needed, which aligns perfectly with pull systems that focus on producing items based on demand. The answer False is incorrect as it contradicts the fundamental principle of Kanban methodology, which emphasizes the pull approach for production scheduling.