IASSC Certified Lean Six Sigma Black Belt (ICBB) — Question 59
Which of these elements are not included in Implementation plans?
Answer options
- A. Work breakdown structure
- B. Risk management plans
- C. Cost/Benefit ratios
- D. Planned audits of work completion
Correct answer: C
Explanation
The correct answer is C, as Cost/Benefit ratios are typically part of the project evaluation phase rather than the Implementation plan itself. The other options, such as Work breakdown structure, Risk management plans, and Planned audits of work completion, are integral components of an Implementation plan, focusing on task organization, risk assessment, and ensuring work meets quality standards.