IASSC Certified Lean Six Sigma Black Belt (ICBB) — Question 59

Which of these elements are not included in Implementation plans?

Answer options

Correct answer: C

Explanation

The correct answer is C, as Cost/Benefit ratios are typically part of the project evaluation phase rather than the Implementation plan itself. The other options, such as Work breakdown structure, Risk management plans, and Planned audits of work completion, are integral components of an Implementation plan, focusing on task organization, risk assessment, and ensuring work meets quality standards.