IASSC Certified Lean Six Sigma Black Belt (ICBB) — Question 50
Which of the following process flow metrics is an essential requirement to calculate ‘productivity’?
Answer options
- A. Effort-related metrics
- B. Defect-related metrics
- C. Cost-variation metrics
- D. Schedule slippage metrics
Correct answer: A
Explanation
Effort-related metrics are vital for calculating productivity as they measure the amount of work put into a process. In contrast, defect-related metrics focus on the quality of the output, cost-variation metrics assess financial aspects, and schedule slippage metrics evaluate timeline adherence, none of which directly measure productivity.