ServiceNow Certified System Administrator — Question 289

Which tables are children of the Task table and come with the base system? (Choose three.)

Answer options

Correct answer: B, E, F

Explanation

The correct answers are B, E, and F because the Problem, Incident, and Change Request tables are all built upon the Task table as part of the base system. Options A and C are not children of the Task table, and option D is a separate configuration management database rather than a direct child.