ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 79
What actions can a project manager perform related to Agile projects on the Details page of Project Workspace? (Choose three.)
Answer options
- A. Create a new Agile phase
- B. View widgets and reports
- C. Add stories
- D. View WBS
- E. Create a Doc page
- F. Remove epics
Correct answer: B, C, D
Explanation
The correct actions a project manager can take on the Details page include viewing widgets and reports (B), adding stories (C), and viewing the WBS (D). Creating a new Agile phase (A), creating a Doc page (E), and removing epics (F) are not typically functions available on the Details page for Agile project management.