ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 73

How can cost plans be generated from resource assignments? (Choose two.)

Answer options

Correct answer: A, C

Explanation

The correct options are A and C because selecting the ‘Generate labor costs’ button in Project Workspace directly creates cost plans from resource assignments, and running a scheduled job automates this process. Options B and D do not directly generate cost plans from resource assignments.