ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 69
Which resource tasks can be completed in Project Workspace? (Choose two.)
Answer options
- A. Create a resource calendar
- B. Allocate a resource creating a named-resource assignment
- C. View resource requests
- D. View available capacity of resources
- E. Request a resource using role, group, or skill
Correct answer: B, E
Explanation
The correct answers are B and E because allocating a resource with a named-resource assignment and requesting a resource using specific criteria are tasks that can be performed within Project Workspace. Options A, C, and D do not pertain to tasks that can be completed in Project Workspace, as they involve different functionalities.