Resource plan costs are divided into: (Choose three.)
Answer options
- A. Planned Cost
- B. Allocated Cost
- C. Actual Cost
- D. Expense Cost
- E. Forecast Cost
Correct answer: A, B, C
Explanation
The correct answers, Planned Cost, Allocated Cost, and Actual Cost, represent different aspects of budgeting and tracking expenses in resource management. Planned Cost refers to what is anticipated, Allocated Cost is what has been designated for specific purposes, and Actual Cost reflects the true expenditures incurred. The other options do not align with standard classifications of resource plan costs.