ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 5
If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following? (Choose two.)
Answer options
- A. Project module
- B. Portfolio Planning Workbench module
- C. Program Workbench
- D. Portfolio Planning related link
Correct answer: B, D
Explanation
The correct answers are B and D because the Portfolio Planning Workbench can be accessed directly through its dedicated module and via the related link specifically for Portfolio Planning. Options A and C are incorrect as they do not provide direct access to the Portfolio Planning Workbench.