ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 33
Where is planned cost calculated from when requesting resources from a group and when resource role is specified?
Answer options
- A. The task rate cards.
- B. The distribution costs.
- C. The hourly rate of the specified role.
- D. The CI rate cards.
Correct answer: C
Explanation
The correct answer is C because the planned cost is derived from the hourly rate associated with the specific role requested. Options A, B, and D do not directly relate to the calculation of the planned cost for a specified resource role.