ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 33

Where is planned cost calculated from when requesting resources from a group and when resource role is specified?

Answer options

Correct answer: C

Explanation

The correct answer is C because the planned cost is derived from the hourly rate associated with the specific role requested. Options A, B, and D do not directly relate to the calculation of the planned cost for a specified resource role.