ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 31
The Project management application supports two types of external dependencies. What are they? (Choose two.)
Answer options
- A. Change Dependency.
- B. Hard Dependency.
- C. Task Dependency.
- D. Soft Dependency.
- E. Milestone Dependency.
Correct answer: B, D
Explanation
The correct answers are B (Hard Dependency) and D (Soft Dependency) because these are the recognized types of external dependencies in project management applications. Options A (Change Dependency), C (Task Dependency), and E (Milestone Dependency) do not represent standard external dependency types in this context.