The Project management application supports two types of external dependencies. What are they? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers are B (Hard Dependency) and D (Soft Dependency) because these are the recognized types of external dependencies in project management applications. Options A (Change Dependency), C (Task Dependency), and E (Milestone Dependency) do not represent standard external dependency types in this context.