ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 29
What is the formula for Forecasted Utilization?
Answer options
- A. Assigned Hours/Capacity
- B. Confirmed Hours/Capacity
- C. (Allocated Hours + Confirmed Hours)/Capacity
- D. Allocated Hours/Capacity
Correct answer: C
Explanation
The correct answer is C because Forecasted Utilization is determined by the sum of Allocated and Confirmed Hours divided by Capacity. Options A and B do not include both necessary components, while option D only considers Allocated Hours, leaving out Confirmed Hours essential for accurate forecasting.