ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 97
You can forecast future costs of projects based on (Choose two.)
Answer options
- A. Actual cost incurred
- B. Changes in project such as project requirements
- C. Incident cost
- D. Paired instances
Correct answer: A, B
Explanation
The correct answers, A and B, are relevant because actual costs provide a historical basis for future budgeting, while changes in project requirements can lead to adjustments in cost projections. Options C and D do not directly relate to forecasting project costs; incident cost is more about unexpected expenses, and paired instances do not have a clear connection to cost estimation.