ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 95
A customer needs to know what activity type is associated to time entries in the project so that they can capitalize build tasks. What is the best method to do this?
Answer options
- A. Leverage project time categories to classify the time.
- B. Create a capital protect task flag.
- C. Put all capital project tasks in one phase and report from those tasks.
- D. Create an incident.
Correct answer: A
Explanation
The correct answer is A, as project time categories help in properly classifying time entries according to their activity type, which is essential for capitalizing build tasks. Options B and D do not provide a classification method and are irrelevant to the task, while option C might help in reporting but does not address the classification needed.