ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 93
Which option should be used if you want to select the resource rate on the resource plan?
Answer options
- A. Rate override
- B. Labor rate card
- C. Rate model
- D. Planned cost
Correct answer: A
Explanation
The correct answer is 'Rate override' because it allows you to specify a different rate for resources than the default. The other options, such as 'Labor rate card' and 'Rate model', do not provide the flexibility to override the existing rate directly, while 'Planned cost' focuses on budgeting rather than rate selection.