ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 80

The project property to update actual effort from time card is controlled at what level?

Answer options

Correct answer: C

Explanation

The correct answer is C, Project Level, as this is where specific project properties, including the management of actual effort updates from time cards, are defined. The other options—Application, Program, and Portfolio Levels—do not directly control project-specific settings.