ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 74

If you want the project planned start date to remain the same despite the start date of the earliest task, what property would you disable?

Answer options

Correct answer: A

Explanation

The correct answer is A because disabling the roll-up of the project start date from tasks ensures that the planned start date remains fixed, independent of task start dates. Options B, C, and D do not directly impact the project's planned start date relative to task starts, making them irrelevant to the question.