ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 74
If you want the project planned start date to remain the same despite the start date of the earliest task, what property would you disable?
Answer options
- A. Roll up project start date from tasks [com.snc.project.rollup_project_start_date].
- B. Max date span into future or past from the current date for the project/project task [com.snc.project.task.check_date_span_years].
- C. Retain start on constraint on tasks after adding relations [com.snc.project.allow_start_on_relations].
- D. Max duration allowed for a project/project task [com.snc.project.task.max_task_duration].
Correct answer: A
Explanation
The correct answer is A because disabling the roll-up of the project start date from tasks ensures that the planned start date remains fixed, independent of task start dates. Options B, C, and D do not directly impact the project's planned start date relative to task starts, making them irrelevant to the question.