Where is planned cost calculated from when requesting resources from a group and when resource role is specified?

Answer options

Correct answer: C

Explanation

The correct answer is C because the planned cost is derived from the hourly rate of the specified role when resources are requested. Options A, B, and D do not directly pertain to the calculation of planned costs based on a specific resource role.