Which capability allows users to view variances in a project’s schedule?

Answer options

Correct answer: C

Explanation

The correct answer is C, as comparing scheduled baselines directly reveals discrepancies between planned and actual timelines. Options A and D do not pertain to schedule variance analysis, while B provides an overview of project status but lacks detailed comparison features.