When creating a resource plan within a demand, how are the default dates on a resource plan determined?

Answer options

Correct answer: A

Explanation

The correct answer is A because the default dates on a resource plan are derived from the demand's start and due dates. Option B is incorrect as resource plans can be created from demands. Options C and D do not accurately reflect how the default dates are established in relation to the demand.