When creating a resource plan within a demand, how are the default dates on a resource plan determined?
Answer options
- A. From demand start date and due date
- B. Resource plan(s) cannot be created from demand
- C. Using demand created date
- D. From portfolio date
Correct answer: A
Explanation
The correct answer is A because the default dates on a resource plan are derived from the demand's start and due dates. Option B is incorrect as resource plans can be created from demands. Options C and D do not accurately reflect how the default dates are established in relation to the demand.