This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.
Answer options
- A. Project form.
- B. Stakeholder registry.
- C. Demand form.
- D. Application registry.
Correct answer: B
Explanation
The correct answer, B. Stakeholder registry, is where the list of stakeholders is managed, allowing for automatic population during project or demand creation. Options A and C refer to forms used for initiating projects or demands, while D is unrelated as it pertains to application management.