ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 2
Is resource capacity derived from FTE or schedules?
Answer options
- A. Only FTE.
- B. Both.
- C. Only Schedules.
- D. Neither.
Correct answer: C
Explanation
The correct answer is C, as resource capacity is specifically derived from the schedules that outline when resources are available. FTE (Full-Time Equivalent) is a measure of work effort rather than a direct source of capacity, making options A and B incorrect. Option D is also incorrect because schedules do indeed contribute to resource capacity.