ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 17
When a time card is approved, the actual time is stored in which two tables? (Choose two.)
Answer options
- A. Project Time table
- B. Resource Allocation Daily table
- C. Resource Event table
- D. Resource Aggregate tables (Daily, Weekly, and Monthly)
Correct answer: B, D
Explanation
The correct answers are B and D because the Resource Allocation Daily table specifically tracks daily resource allocations, while the Resource Aggregate tables store summarized data over various time frames. Options A and C are incorrect as they do not pertain to the storage of actual time once a time card is approved.