ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 151

When creating a program, which of the following cannot be part of multiple programs? (Choose two.)

Answer options

Correct answer: B, C

Explanation

The correct answers are B and C because a Project is a unique entity within a program and cannot be shared across multiple programs. Similarly, Demand is specific to a single program's requirements and cannot appear in multiple programs, while Tasks and Portfolio can be associated with various programs.