ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 144

When Agile Development 2.0 and Test Management 2.0 plugins are activated, the project manager can create and edit which of the following phase types depending on execution type? (Choose two.)

Answer options

Correct answer: A, B

Explanation

The correct answers are A and B because the Agile Development and Test Management plugins specifically allow the creation and modification of Test and Agile phases. Options C and D are not applicable for this context as they do not align with the functionalities provided by the activated plugins.