ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 137

Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)

Answer options

Correct answer: B, D

Explanation

Option B is correct because it accurately states that when the project state is Pending or Open, the planned start and end dates are displayed. Option D is also correct as it indicates that during the Work in Progress state, the actual start date and planned end date are shown. Options A and C are incorrect because they describe behaviors for project states that do not match the requirements for displaying dynamic content.